Codes, Permits & Approvals
Codes, Permits & Plan Approvals: Questions & Answers
Short answers for owners, architects and contractors planning around code transitions, permit applications and plan approvals.
Get a ProposalAnswers are grouped by topic below. Requirements vary by jurisdiction and project, so confirm them with the authority responsible for the property.
Code Transitions
These answers summarize our article Building Code Changes for 2026 and 2027. They are general information, not a determination for any project: local adoption and transition rules control, and each project needs its own review with the authority having jurisdiction.
Is there one national 2027 code deadline?
No. There is no single nationwide January 2027 code deadline. States and local jurisdictions adopt and transition codes on their own schedules, so a project's location drives its code-transition plan.
Does construction need to finish before a code changes?
Not necessarily. Finishing design, submitting an application, obtaining a permit and completing construction are different milestones. Which one determines the applicable code depends on the jurisdiction's rules.
Does submitting drawings preserve the old code?
It should not be assumed. Some rules depend on an application being complete or accepted for review, a permit being issued, or other conditions. There is no guaranteed grandfathering; confirm the exact milestone and documentation required with the building department.
Which authority decides which code applies?
The authority having jurisdiction — typically the state or local building department that administers permits for the project — together with the adopted codes, local amendments and transition rules it enforces.
Can a schedule delay cause redesign?
Yes. If a project misses the required permit milestone, it may become subject to the newer code edition. The team then has to determine which changes affect it, and where revisions are needed that can mean rechecking calculations, revising drawings and recoordinating disciplines.
Must every project be redesigned under a new code?
No. Redesign is a potential consequence, not a certainty. The impact depends on the adopted provisions, local amendments, building use, site and design stage. Even where the design remains acceptable, the assessment itself takes time.
Do renovations follow the same rules as new buildings?
Not always. Alterations, additions and changes of use can be governed by existing-building provisions and local rules that differ from new construction. Applicability to a renovation needs the same project-specific confirmation with the jurisdiction.
Can permit expiration, scope changes or phased permits affect the applicable code?
They can. Teams should understand permit validity, and how later revisions, scope changes or phased applications are treated, because these can alter eligibility under the earlier requirements.
Do model codes automatically become law?
No. Model codes such as the International Codes and the National Electrical Code take effect only when a state or local government adopts them, often with amendments and an effective date of its own.
What are the confirmed South Carolina, Washington and Chicago dates?
South Carolina: January 1, 2027 — the state's amended 2024 building, residential, fire, mechanical, plumbing and fuel-gas codes and the 2023 National Electrical Code. Local jurisdictions administer permit procedures, so confirm transition requirements with the building department.
Washington: December 31, 2026 — the adopted electrical rule replaces the 2023 NEC with the 2026 NEC, with exceptions for certain projects with earlier building permits or electrical plans received and accepted for review before the transition.
Chicago: December 1, 2026 — new mechanical, fuel-gas and energy provisions become mandatory for permit applications started on or after this date, subject to transition exceptions. This is city-specific, not an Illinois-wide deadline.
What information should a project team gather?
Which code editions and amendments apply today; what changes take effect, and when; the exact milestone that preserves eligibility under current requirements; what documentation must be complete to reach it; and whether expiration, scope changes or later phases could alter that eligibility.
Also list unresolved owner decisions, outstanding calculations, missing consultant information and coordination issues, then work backward from the confirmed deadline allowing time for quality review, signatures and seals where required, document assembly and intake.
How can VizoDesign assist with upcoming code changes?
VizoDesign can assist architectural firms, owners, and project teams with structural, MEP, and BIM design support as they prepare for upcoming code changes. We can review the current design stage, identify outstanding deliverables, coordinate drawings across disciplines, and help establish a practical schedule for permit submission. Share your project location, current plans, and target submission date so we can assess the remaining work and recommend the right support. Applicable code requirements and permit milestones should be confirmed with the authority having jurisdiction.
Code-transition sources
- South Carolina Building Codes Council — 2024 Code Adoption Notice (opens in a new tab)
- Washington State Register WSR 25-23-069 — electrical rule (2026 NEC) (opens in a new tab)
- City of Chicago Department of Buildings — Phase 3 code alert (October 2026) (opens in a new tab)
Code-transition information checked November 4, 2026. Confirm project applicability and permit requirements with the authority having jurisdiction.
Permits and Plan Approvals
Local and project-specific requirements control. City examples apply only within that city and are not national rules; confirm current requirements, fees and timelines with the authority responsible for the property.
For a step-by-step walkthrough, read our guide How to Navigate Building Permits and City Plan Approvals.
Do I need a permit for a renovation or tenant improvement?
Permit requirements depend on the location and scope. Structural changes, changes to building systems, additions and changes of use can trigger permits or additional reviews. Some minor work may be exempt from a permit or qualify for a simplified process. Confirm the applicable requirements with the authority responsible for the property before starting work.
What is the difference between zoning approval, plan approval and a building permit?
Zoning review checks whether the proposed use and development comply with land-use rules. Building plan review checks the submitted design against applicable construction requirements. Permit issuance authorizes the approved work, subject to its conditions. These steps may involve different departments, and approval at one step does not complete the others.
What should I prepare before submitting plans?
Confirm the jurisdiction, proposed use, project scope, applicable codes, zoning constraints and submission checklist. Assemble the required drawings, calculations, forms and supporting reports. Coordinate architectural, structural, and mechanical, electrical and plumbing information so the documents describe the same project.
Can VizoDesign help with permit-ready engineering documents and review comments?
VizoDesign provides structural and MEP engineering services, including coordinated design documents and permit-response support as agreed in the project scope. Required architectural, civil, survey, geotechnical and other specialist services should be identified separately. The reviewing authority makes all permit and approval decisions.
How long does permit approval take?
There is no single approval timeline. Timing depends on the jurisdiction, permit type, project complexity, application completeness, required agency reviews and correction cycles. Ask about current review expectations for the specific application and allow time for responses, resubmittals and permit issuance. A first-review estimate is not an approval date.
What can make permitting more complicated in Los Angeles?
For projects within the City of Los Angeles, parcel-specific zoning rules, overlays, planning conditions and departmental clearances can affect the approval path. Start with ZIMAS, confirm applicable requirements, and track required clearances alongside LADBS plan review. Los Angeles County and neighboring cities may have different authorities and procedures.
What should I check before leasing or renovating a commercial space in Dallas?
Confirm that the proposed use is allowed at the specific property, including any Planned Development district or overlay requirements. Review the existing Certificate of Occupancy and ask what is required for the new tenant, use or floor area. The City of Dallas uses DallasNow for permit and CO applications; a previous tenant’s approval does not automatically cover a new business.
How should the team respond to plan-review comments?
Use a comment log that identifies each issue, the responsible team member, the response and the revised drawing or calculation. Coordinate changes across all affected disciplines, follow the authority’s resubmittal instructions, and request clarification when a comment is unclear. Retain the approved revision history for construction.
Can construction begin when the plans are approved?
Confirm that the required permits have actually been issued and that any conditions for starting work are satisfied. During construction, follow the approved documents and inspection requirements. Final inspections and a Certificate of Occupancy or other completion approval may be required before the space can be occupied or used.
Permit and approval sources
- Los Angeles City Planning — Zoning search (ZIMAS) (opens in a new tab)
- LADBS — Plan Review & Permitting (opens in a new tab)
- LADBS — About the construction process (opens in a new tab)
- City of Dallas Planning & Development — Zoning resources (opens in a new tab)
- City of Dallas — Development guide (opens in a new tab)
- City of Dallas — Certificate of Occupancy (opens in a new tab)
Permit and approval information checked November 10, 2026. Local procedures change; confirm current requirements with the reviewing authority.